February 2021
- Suprastructure works:
- Steel construction works are completed. 100% of the metallic structure elements are mounted.
- Works inside are in progress.
- Exterior works are in progress.
- Rail infrastructure:
- Construction works for the rail infrasructure inside the logistics center are in progress.
- Mobile Equipment:
- Both cranes have already been lifted onto the crane runway.