January 2022

  • Official start of the logistics services



October 2021

  • Official Opening Ceremony of the trimodal Logistics Center



September 2021

  • Suprastructure works:

    • Exterior works are in progress.



August 2021

  • Suprastructure works:

    • Exterior works are in progress.



July 2021

  • Suprastructure works:

    • Exterior works are in progress.





June 2021

  • Suprastructure works:

    • Works inside are completed.
    • Exterior works are in progress.

  • Mobile Equipment:

    • Both cranes have been installed.

  • Warehouse Equipment:

    • Beginning of the construction of the storage facilities.

 



May 2021

  • Suprastructure works:

    • Works inside are nearly completed.
    • Exterior works are in progress.

  • Mobile Equipment:

    • Two forklifts were delivered.
    • Works to put the crane into operation are in progress.

  • Warehouse Equipment:

    • Beginning of the construction of the storage facilities.



April 2021

  • Suprastructure works:

    • Works inside the logistics center are nearly completed.
    • Exterior works are in progress.

 



March 2021

  • Suprastructure works:

    • The execusions of the exterior works are in progress.
    • Works inside are in progress.

 



February 2021

  • Suprastructure works:

    • Steel construction works are completed. 100% of the metallic structure elements are mounted.
    • Works inside are in progress.
    • Exterior works are in progress.

  • Rail infrastructure:

    • Construction works for the rail infrasructure inside the logistics center are in progress.

  • Mobile Equipment:

    • Both cranes have already been lifted onto the crane runway.

 



January 2021

  • Suprastructure works:

    • Steel construction works are completed. 100% of the metallic structure elements are mounted.
    • Works inside are in progress.
    • Exterior works are in progress.

  • Rail infrastructure:

    • Construction works for the rail infrasructure inside the logistics center are in progress.



December 2020

  • Suprastructure works:

    • Steel construction works are ongoing. About 98% of the metallic structure elements are already mounted.
    • works inside the logistics center are in progress



November 2020

  • Suprastructure works:

    • Steel construction works are ongoing. About 90% of the metallic structure elements are already mounted.
    • Works inside the logistics center are in progress



October 2020

  • Suprastructure works:

    • Steel construction works are ongoing. About 85% of the metallic structure elements are already mounted.

 



September 2020

  • Suprastructure works:

    • Steel construction works are ongoing. About 70% of the metallic structure elements are already mounted.

  • Infrastructure works:

    • The removal of the cofferdam is completed.
    • Backfilling works and bank protection works are completed.

         

 



July/August 2020

  • Suprastructure works:

    • Steel construction works are ongoing. More than 50% of the metallic structure elements are already mounted.

  • Infrastructure works:

    • The removal of the cofferdam started.
    • Backfilling works and bank protection works are nearly completed.

         



June 2020

  • Suprastructure works:

    • steel construction works

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

         



May 2020

  • Suprastructure works:

    • steel construction works

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition is finished

       

 



April 2020

  • Suprastructure works:

    • steel construction works

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition

       

 



March 2020

  • Suprastructure works:

    • steel construction works

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition

       

 



February 2020

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition
  • Suprastructure works:

    • steel consruction works



January 2020

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition
  • Suprastructure works:

    • steel consruction works



December 2019

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition
  • Suprastructure works:

    • Beginning steel construction works



November 2019

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition



October 2019

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition
 



September 2019

  • Infrastructure works:

    • Concreting mooring basin
    • Work on conrete piles for mooring basin, logistics center area and bank protection
    • Backfilling works

  • Road Rehabilition
 



August 2019

- Infrastructure works

- Road Rehabilitation

 



July 2019

- Infrastructure works

 



June 2019

- Infrastructure works

 



May 2019

- Infrastructure works



April 2019

- Infrastructure works



October / November 2018

- Backfilling

 



September 2018

- Railway line construction finished

 



July 2018

  - railway line construction

 



June 2018

  - railway line construction



May 2018

  - railway line construction

 



April 2018

  - Start of railway line construction



February 2018

  - Consolidation of the demolition works

 



August / September 2017

  - Protection neighbor-property



June / July 2017

  - Drainage construction site (within the cofferdam)



May 2017

  - Completion of cofferdam and last demolition works

 



April 2017

  - Cofferdam construction



March 2017

  - Cofferdam construction

 



February 2017

  - Continuation of demolition work and excavation work



January 2017

  - Winter in Giurgiu (cold and snow) – restricted construction work



December 2016

  - Demolition of concrete pile foundations
  - Excavation works



November 2016

  - Demolition of concrete pile foundations
  - Excavation works



October 2016

   - Demolition of concrete pile foundations
   - Start of earth dredging



September 2016

  - Demolition of concrete piles
  - Storage of dismantled steel elements



August 2016

  - Clearing of the srub
  - Dismantling of the old steel structure



July 2016

  - Start of demolition work to prepare the site
  - Installation of the building site and access to the construction site