January 2022
- Official start of the logistics services
October 2021
- Official Opening Ceremony of the trimodal Logistics Center
September 2021
- Suprastructure works:
- Exterior works are in progress.
August 2021
- Suprastructure works:
- Exterior works are in progress.
July 2021
- Suprastructure works:
- Exterior works are in progress.
June 2021
- Suprastructure works:
- Works inside are completed.
- Exterior works are in progress.
- Mobile Equipment:
- Both cranes have been installed.
- Warehouse Equipment:
- Beginning of the construction of the storage facilities.
May 2021
- Suprastructure works:
- Works inside are nearly completed.
- Exterior works are in progress.
- Mobile Equipment:
- Two forklifts were delivered.
- Works to put the crane into operation are in progress.
- Warehouse Equipment:
- Beginning of the construction of the storage facilities.
April 2021
- Suprastructure works:
- Works inside the logistics center are nearly completed.
- Exterior works are in progress.
March 2021
- Suprastructure works:
- The execusions of the exterior works are in progress.
- Works inside are in progress.
February 2021
- Suprastructure works:
- Steel construction works are completed. 100% of the metallic structure elements are mounted.
- Works inside are in progress.
- Exterior works are in progress.
- Rail infrastructure:
- Construction works for the rail infrasructure inside the logistics center are in progress.
- Mobile Equipment:
- Both cranes have already been lifted onto the crane runway.
January 2021
- Suprastructure works:
- Steel construction works are completed. 100% of the metallic structure elements are mounted.
- Works inside are in progress.
- Exterior works are in progress.
- Rail infrastructure:
- Construction works for the rail infrasructure inside the logistics center are in progress.
December 2020
- Suprastructure works:
- Steel construction works are ongoing. About 98% of the metallic structure elements are already mounted.
- works inside the logistics center are in progress
November 2020
- Suprastructure works:
- Steel construction works are ongoing. About 90% of the metallic structure elements are already mounted.
- Works inside the logistics center are in progress
October 2020
- Suprastructure works:
- Steel construction works are ongoing. About 85% of the metallic structure elements are already mounted.
September 2020
- Suprastructure works:
- Steel construction works are ongoing. About 70% of the metallic structure elements are already mounted.
- Infrastructure works:
- The removal of the cofferdam is completed.
- Backfilling works and bank protection works are completed.
July/August 2020
- Suprastructure works:
- Steel construction works are ongoing. More than 50% of the metallic structure elements are already mounted.
- Infrastructure works:
- The removal of the cofferdam started.
- Backfilling works and bank protection works are nearly completed.
June 2020
- Suprastructure works:
- steel construction works
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
May 2020
- Suprastructure works:
- steel construction works
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition is finished
April 2020
- Suprastructure works:
- steel construction works
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
March 2020
- Suprastructure works:
- steel construction works
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
February 2020
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
- Suprastructure works:
- steel consruction works
January 2020
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
- Suprastructure works:
- steel consruction works
December 2019
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
- Suprastructure works:
- Beginning steel construction works
November 2019
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
October 2019
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
September 2019
- Infrastructure works:
- Concreting mooring basin
- Work on conrete piles for mooring basin, logistics center area and bank protection
- Backfilling works
- Road Rehabilition
August 2019
- Infrastructure works
- Road Rehabilitation
July 2019
- Infrastructure works
June 2019
- Infrastructure works
May 2019
- Infrastructure works
April 2019
- Infrastructure works
October / November 2018
- Backfilling
September 2018
- Railway line construction finished
July 2018
- railway line construction
June 2018
- railway line construction
May 2018
- railway line construction
April 2018
- Start of railway line construction
February 2018
- Consolidation of the demolition works
August / September 2017
- Protection neighbor-property
June / July 2017
- Drainage construction site (within the cofferdam)
May 2017
- Completion of cofferdam and last demolition works
April 2017
- Cofferdam construction
March 2017
- Cofferdam construction
February 2017
- Continuation of demolition work and excavation work
January 2017
- Winter in Giurgiu (cold and snow) – restricted construction work
December 2016
- Demolition of concrete pile foundations
- Excavation works
November 2016
- Demolition of concrete pile foundations
- Excavation works
October 2016
- Demolition of concrete pile foundations
- Start of earth dredging
September 2016
- Demolition of concrete piles
- Storage of dismantled steel elements
August 2016
- Clearing of the srub
- Dismantling of the old steel structure
July 2016
- Start of demolition work to prepare the site
- Installation of the building site and access to the construction site